Contracted Terms
130 clause-level terms extracted from customer agreements
Terms recorded
130
Non-standard
14
Accounts covered
13
Term categories
10
130 of 130 terms
| Category | Account | Term | Value | Source and clause | Effective | Position |
|---|---|---|---|---|---|---|
| Power | Hyperscaler A | Maximum IT load density per rack | Max 50 kW per rack, N+1 supply | C-2001 Hyperscaler A APAC MSA Sched 2, cl 3.1 | 2019-04-01 | Standard |
| Cooling | Hyperscaler A | Cooling method and supply temperature | Air cooled, 27°C supply | C-2001 Hyperscaler A APAC MSA Sched 2, cl 4.2 | 2019-04-01 | Standard |
| Connectivity | Hyperscaler A | Diverse fibre entry into the building | 4 diverse fibre entry points | C-2001 Hyperscaler A APAC MSA Sched 3, cl 2.4 | 2019-04-01 | Non-standard |
| Space | Hyperscaler A | Dedicated space allocation | Dedicated hall, caged, 210 MW | C-2001 Hyperscaler A APAC MSA Sched 1, cl 1.2 | 2019-04-01 | Standard |
| SLA and service credits | Hyperscaler A | Availability target and credit regime | 99.999% uptime, 5% credit per 0.01% | C-2001 Hyperscaler A APAC MSA Sched 5, cl 2.1 | 2019-04-01 | Standard |
| Expansion rights and ROFR | Hyperscaler A | Right of first refusal on further capacity | ROFR on adjacent hall, 30 day response | C-2001 Hyperscaler A APAC MSA cl 14.3 | 2019-04-01 | Standard |
| Pricing and indexation | Hyperscaler A | Annual price adjustment | CPI indexation, capped at 3% a year | C-2001 Hyperscaler A APAC MSA cl 8.5 | 2019-04-01 | Standard |
| Sustainability and renewable energy commitments | Hyperscaler A | Renewable energy matching | 100% renewable energy matched annually | C-2001 Hyperscaler A APAC MSA Sched 7, cl 1.1 | 2019-04-01 | Standard |
| Security and access | Hyperscaler A | Physical access control | Biometric access, escorted visitors | C-2001 Hyperscaler A APAC MSA Sched 6, cl 3.2 | 2019-04-01 | Standard |
| Termination and step-in | Hyperscaler A | Termination rights and cure period | Termination for cause, 90 day cure | C-2001 Hyperscaler A APAC MSA cl 21.1 | 2019-04-01 | Standard |
| Power | Hyperscaler B | Maximum IT load density per rack | Max 50 kW per rack, N+1 supply | C-2004 Campus North-1 Hall B lease Sched 2, cl 3.1 | 2021-03-01 | Standard |
| Cooling | Hyperscaler B | Cooling method and supply temperature | Air cooled, 27°C supply | C-2004 Campus North-1 Hall B lease Sched 2, cl 4.2 | 2021-03-01 | Standard |
| Connectivity | Hyperscaler B | Diverse fibre entry into the building | 2 diverse fibre entry points | C-2004 Campus North-1 Hall B lease Sched 3, cl 2.4 | 2021-03-01 | Standard |
| Space | Hyperscaler B | Dedicated space allocation | Dedicated hall, caged, 45 MW | C-2004 Campus North-1 Hall B lease Sched 1, cl 1.2 | 2021-03-01 | Standard |
| SLA and service credits | Hyperscaler B | Availability target and credit regime | 99.999% uptime, 10% credit per 0.01% | C-2004 Campus North-1 Hall B lease Sched 5, cl 2.1 | 2021-03-01 | Non-standard |
| Expansion rights and ROFR | Hyperscaler B | Right of first refusal on further capacity | ROFR on adjacent hall, 30 day response | C-2004 Campus North-1 Hall B lease cl 14.3 | 2021-03-01 | Standard |
| Pricing and indexation | Hyperscaler B | Annual price adjustment | CPI indexation, capped at 3% a year | C-2004 Campus North-1 Hall B lease cl 8.5 | 2021-03-01 | Standard |
| Sustainability and renewable energy commitments | Hyperscaler B | Renewable energy matching | 100% renewable energy matched annually | C-2004 Campus North-1 Hall B lease Sched 7, cl 1.1 | 2021-03-01 | Standard |
| Security and access | Hyperscaler B | Physical access control | Biometric access, escorted visitors | C-2004 Campus North-1 Hall B lease Sched 6, cl 3.2 | 2021-03-01 | Standard |
| Termination and step-in | Hyperscaler B | Termination rights and cure period | Termination for cause, 90 day cure | C-2004 Campus North-1 Hall B lease cl 21.1 | 2021-03-01 | Standard |
| Power | Hyperscaler C | Maximum IT load density per rack | Max 50 kW per rack, N+1 supply | C-2005 Campus South-1 Hall A lease Sched 2, cl 3.1 | 2021-09-01 | Standard |
| Cooling | Hyperscaler C | Cooling method and supply temperature | Air cooled, 27°C supply | C-2005 Campus South-1 Hall A lease Sched 2, cl 4.2 | 2021-09-01 | Standard |
| Connectivity | Hyperscaler C | Diverse fibre entry into the building | 2 diverse fibre entry points | C-2005 Campus South-1 Hall A lease Sched 3, cl 2.4 | 2021-09-01 | Standard |
| Space | Hyperscaler C | Dedicated space allocation | Dedicated hall, caged, 40 MW | C-2005 Campus South-1 Hall A lease Sched 1, cl 1.2 | 2021-09-01 | Standard |
| SLA and service credits | Hyperscaler C | Availability target and credit regime | 99.999% uptime, 5% credit per 0.01% | C-2005 Campus South-1 Hall A lease Sched 5, cl 2.1 | 2021-09-01 | Standard |
| Expansion rights and ROFR | Hyperscaler C | Right of first refusal on further capacity | ROFR on adjacent hall, 30 day response | C-2005 Campus South-1 Hall A lease cl 14.3 | 2021-09-01 | Standard |
| Pricing and indexation | Hyperscaler C | Annual price adjustment | CPI indexation, capped at 3% a year | C-2005 Campus South-1 Hall A lease cl 8.5 | 2021-09-01 | Standard |
| Sustainability and renewable energy commitments | Hyperscaler C | Renewable energy matching | 100% renewable energy matched annually | C-2005 Campus South-1 Hall A lease Sched 7, cl 1.1 | 2021-09-01 | Standard |
| Security and access | Hyperscaler C | Physical access control | Biometric access, escorted visitors | C-2005 Campus South-1 Hall A lease Sched 6, cl 3.2 | 2021-09-01 | Standard |
| Termination and step-in | Hyperscaler C | Termination rights and cure period | Termination for cause, 90 day cure | C-2005 Campus South-1 Hall A lease cl 21.1 | 2021-09-01 | Standard |
| Power | Hyperscaler D | Maximum IT load density per rack | Max 50 kW per rack, N+1 supply | C-2010 Campus East-1 power uplift amendment Sched 2, cl 3.1 | 2026-01-01 | Standard |
| Cooling | Hyperscaler D | Cooling method and supply temperature | Air cooled, 27°C supply | C-2010 Campus East-1 power uplift amendment Sched 2, cl 4.2 | 2026-01-01 | Standard |
| Connectivity | Hyperscaler D | Diverse fibre entry into the building | 2 diverse fibre entry points | C-2010 Campus East-1 power uplift amendment Sched 3, cl 2.4 | 2026-01-01 | Standard |
| Space | Hyperscaler D | Dedicated space allocation | Dedicated hall, caged, 10 MW | C-2010 Campus East-1 power uplift amendment Sched 1, cl 1.2 | 2026-01-01 | Standard |
| SLA and service credits | Hyperscaler D | Availability target and credit regime | 99.999% uptime, 5% credit per 0.01% | C-2010 Campus East-1 power uplift amendment Sched 5, cl 2.1 | 2026-01-01 | Standard |
| Expansion rights and ROFR | Hyperscaler D | Right of first refusal on further capacity | ROFR on adjacent hall, 30 day response | C-2010 Campus East-1 power uplift amendment cl 14.3 | 2026-01-01 | Standard |
| Pricing and indexation | Hyperscaler D | Annual price adjustment | CPI indexation, capped at 3% a year | C-2010 Campus East-1 power uplift amendment cl 8.5 | 2026-01-01 | Standard |
| Sustainability and renewable energy commitments | Hyperscaler D | Renewable energy matching | 100% renewable energy matched annually | C-2010 Campus East-1 power uplift amendment Sched 7, cl 1.1 | 2026-01-01 | Standard |
| Security and access | Hyperscaler D | Physical access control | Sovereign cleared staff only, no remote hands | C-2010 Campus East-1 power uplift amendment Sched 6, cl 3.2 | 2026-01-01 | Non-standard |
| Termination and step-in | Hyperscaler D | Termination rights and cure period | Termination for cause, 90 day cure | C-2010 Campus East-1 power uplift amendment cl 21.1 | 2026-01-01 | Standard |
| Power | Platform E | Maximum IT load density per rack | Max 50 kW per rack, N+1 supply | C-2014 Platform E APAC MSA Sched 2, cl 3.1 | 2023-01-01 | Standard |
| Cooling | Platform E | Cooling method and supply temperature | Air cooled, 27°C supply | C-2014 Platform E APAC MSA Sched 2, cl 4.2 | 2023-01-01 | Standard |
| Connectivity | Platform E | Diverse fibre entry into the building | 2 diverse fibre entry points | C-2014 Platform E APAC MSA Sched 3, cl 2.4 | 2023-01-01 | Standard |
| Space | Platform E | Dedicated space allocation | Dedicated hall, caged, 95 MW | C-2014 Platform E APAC MSA Sched 1, cl 1.2 | 2023-01-01 | Standard |
| SLA and service credits | Platform E | Availability target and credit regime | 99.999% uptime, 5% credit per 0.01% | C-2014 Platform E APAC MSA Sched 5, cl 2.1 | 2023-01-01 | Standard |
| Expansion rights and ROFR | Platform E | Right of first refusal on further capacity | ROFR on adjacent hall, 30 day response | C-2014 Platform E APAC MSA cl 14.3 | 2023-01-01 | Standard |
| Pricing and indexation | Platform E | Annual price adjustment | CPI indexation, capped at 3% a year | C-2014 Platform E APAC MSA cl 8.5 | 2023-01-01 | Standard |
| Sustainability and renewable energy commitments | Platform E | Renewable energy matching | 24/7 carbon-free energy by 2030 | C-2014 Platform E APAC MSA Sched 7, cl 1.1 | 2023-01-01 | Non-standard |
| Security and access | Platform E | Physical access control | Biometric access, escorted visitors | C-2014 Platform E APAC MSA Sched 6, cl 3.2 | 2023-01-01 | Standard |
| Termination and step-in | Platform E | Termination rights and cure period | Termination for cause, 90 day cure | C-2014 Platform E APAC MSA cl 21.1 | 2023-01-01 | Standard |
| Power | Platform F | Maximum IT load density per rack | Max 50 kW per rack, N+1 supply | C-2018 Campus North-1 storage sale order Sched 2, cl 3.1 | 2026-11-01 | Standard |
| Cooling | Platform F | Cooling method and supply temperature | Air cooled, 27°C supply | C-2018 Campus North-1 storage sale order Sched 2, cl 4.2 | 2026-11-01 | Standard |
| Connectivity | Platform F | Diverse fibre entry into the building | 2 diverse fibre entry points | C-2018 Campus North-1 storage sale order Sched 3, cl 2.4 | 2026-11-01 | Standard |
| Space | Platform F | Dedicated space allocation | Dedicated hall, caged, 15 MW | C-2018 Campus North-1 storage sale order Sched 1, cl 1.2 | 2026-11-01 | Standard |
| SLA and service credits | Platform F | Availability target and credit regime | 99.999% uptime, 5% credit per 0.01% | C-2018 Campus North-1 storage sale order Sched 5, cl 2.1 | 2026-11-01 | Standard |
| Expansion rights and ROFR | Platform F | Right of first refusal on further capacity | ROFR on adjacent hall, 30 day response | C-2018 Campus North-1 storage sale order cl 14.3 | 2026-11-01 | Standard |
| Pricing and indexation | Platform F | Annual price adjustment | CPI indexation, capped at 3% a year | C-2018 Campus North-1 storage sale order cl 8.5 | 2026-11-01 | Standard |
| Sustainability and renewable energy commitments | Platform F | Renewable energy matching | 100% renewable energy matched annually | C-2018 Campus North-1 storage sale order Sched 7, cl 1.1 | 2026-11-01 | Standard |
| Security and access | Platform F | Physical access control | Biometric access, escorted visitors | C-2018 Campus North-1 storage sale order Sched 6, cl 3.2 | 2026-11-01 | Standard |
| Termination and step-in | Platform F | Termination rights and cure period | Termination for cause, 90 day cure | C-2018 Campus North-1 storage sale order cl 21.1 | 2026-11-01 | Standard |
| Power | Platform G | Maximum IT load density per rack | Max 50 kW per rack, N+1 supply | C-2009 Campus Harbour-1 Hall A lease Sched 2, cl 3.1 | 2020-05-01 | Standard |
| Cooling | Platform G | Cooling method and supply temperature | Air cooled, 27°C supply | C-2009 Campus Harbour-1 Hall A lease Sched 2, cl 4.2 | 2020-05-01 | Standard |
| Connectivity | Platform G | Diverse fibre entry into the building | 2 diverse fibre entry points | C-2009 Campus Harbour-1 Hall A lease Sched 3, cl 2.4 | 2020-05-01 | Standard |
| Space | Platform G | Dedicated space allocation | Dedicated hall, caged, 40 MW | C-2009 Campus Harbour-1 Hall A lease Sched 1, cl 1.2 | 2020-05-01 | Standard |
| SLA and service credits | Platform G | Availability target and credit regime | 99.999% uptime, 5% credit per 0.01% | C-2009 Campus Harbour-1 Hall A lease Sched 5, cl 2.1 | 2020-05-01 | Standard |
| Expansion rights and ROFR | Platform G | Right of first refusal on further capacity | ROFR on adjacent hall, 30 day response | C-2009 Campus Harbour-1 Hall A lease cl 14.3 | 2020-05-01 | Standard |
| Pricing and indexation | Platform G | Annual price adjustment | Fixed price, no indexation for 6 years | C-2009 Campus Harbour-1 Hall A lease cl 8.5 | 2020-05-01 | Non-standard |
| Sustainability and renewable energy commitments | Platform G | Renewable energy matching | 100% renewable energy matched annually | C-2009 Campus Harbour-1 Hall A lease Sched 7, cl 1.1 | 2020-05-01 | Standard |
| Security and access | Platform G | Physical access control | Biometric access, escorted visitors | C-2009 Campus Harbour-1 Hall A lease Sched 6, cl 3.2 | 2020-05-01 | Standard |
| Termination and step-in | Platform G | Termination rights and cure period | Termination for cause, 90 day cure | C-2009 Campus Harbour-1 Hall A lease cl 21.1 | 2020-05-01 | Standard |
| Power | Regional Cloud H | Maximum IT load density per rack | Max 50 kW per rack, N+1 supply | C-2013 Campus Harbour-1 Hall B lease Sched 2, cl 3.1 | 2023-04-01 | Standard |
| Cooling | Regional Cloud H | Cooling method and supply temperature | Air cooled, 27°C supply | C-2013 Campus Harbour-1 Hall B lease Sched 2, cl 4.2 | 2023-04-01 | Standard |
| Connectivity | Regional Cloud H | Diverse fibre entry into the building | 2 diverse fibre entry points | C-2013 Campus Harbour-1 Hall B lease Sched 3, cl 2.4 | 2023-04-01 | Standard |
| Space | Regional Cloud H | Dedicated space allocation | Dedicated hall, caged, 25 MW | C-2013 Campus Harbour-1 Hall B lease Sched 1, cl 1.2 | 2023-04-01 | Standard |
| SLA and service credits | Regional Cloud H | Availability target and credit regime | 99.999% uptime, 5% credit per 0.01% | C-2013 Campus Harbour-1 Hall B lease Sched 5, cl 2.1 | 2023-04-01 | Standard |
| Expansion rights and ROFR | Regional Cloud H | Right of first refusal on further capacity | ROFR on adjacent hall, 30 day response | C-2013 Campus Harbour-1 Hall B lease cl 14.3 | 2023-04-01 | Standard |
| Pricing and indexation | Regional Cloud H | Annual price adjustment | CPI indexation, capped at 3% a year | C-2013 Campus Harbour-1 Hall B lease cl 8.5 | 2023-04-01 | Standard |
| Sustainability and renewable energy commitments | Regional Cloud H | Renewable energy matching | 100% renewable energy matched annually | C-2013 Campus Harbour-1 Hall B lease Sched 7, cl 1.1 | 2023-04-01 | Standard |
| Security and access | Regional Cloud H | Physical access control | Biometric access, escorted visitors | C-2013 Campus Harbour-1 Hall B lease Sched 6, cl 3.2 | 2023-04-01 | Standard |
| Termination and step-in | Regional Cloud H | Termination rights and cure period | Termination for cause, 90 day cure | C-2013 Campus Harbour-1 Hall B lease cl 21.1 | 2023-04-01 | Standard |
| Power | Regional Cloud I | Maximum IT load density per rack | Max 50 kW per rack, N+1 supply | C-2011 Campus Bay-1 Hall A lease Sched 2, cl 3.1 | 2019-01-01 | Standard |
| Cooling | Regional Cloud I | Cooling method and supply temperature | Air cooled, 27°C supply | C-2011 Campus Bay-1 Hall A lease Sched 2, cl 4.2 | 2019-01-01 | Standard |
| Connectivity | Regional Cloud I | Diverse fibre entry into the building | 2 diverse fibre entry points | C-2011 Campus Bay-1 Hall A lease Sched 3, cl 2.4 | 2019-01-01 | Standard |
| Space | Regional Cloud I | Dedicated space allocation | Dedicated hall, caged, 30 MW | C-2011 Campus Bay-1 Hall A lease Sched 1, cl 1.2 | 2019-01-01 | Standard |
| SLA and service credits | Regional Cloud I | Availability target and credit regime | 99.999% uptime, 5% credit per 0.01% | C-2011 Campus Bay-1 Hall A lease Sched 5, cl 2.1 | 2019-01-01 | Standard |
| Expansion rights and ROFR | Regional Cloud I | Right of first refusal on further capacity | ROFR on adjacent hall, 30 day response | C-2011 Campus Bay-1 Hall A lease cl 14.3 | 2019-01-01 | Standard |
| Pricing and indexation | Regional Cloud I | Annual price adjustment | CPI indexation, capped at 3% a year | C-2011 Campus Bay-1 Hall A lease cl 8.5 | 2019-01-01 | Standard |
| Sustainability and renewable energy commitments | Regional Cloud I | Renewable energy matching | 100% renewable energy matched annually | C-2011 Campus Bay-1 Hall A lease Sched 7, cl 1.1 | 2019-01-01 | Standard |
| Security and access | Regional Cloud I | Physical access control | Biometric access, escorted visitors | C-2011 Campus Bay-1 Hall A lease Sched 6, cl 3.2 | 2019-01-01 | Standard |
| Termination and step-in | Regional Cloud I | Termination rights and cure period | Termination for cause, 90 day cure | C-2011 Campus Bay-1 Hall A lease cl 21.1 | 2019-01-01 | Standard |
| Power | Regional Cloud J | Maximum IT load density per rack | Max 50 kW per rack, N+1 supply | C-2012 Campus Bay-1 Hall B lease Sched 2, cl 3.1 | 2022-01-01 | Standard |
| Cooling | Regional Cloud J | Cooling method and supply temperature | Air cooled, 27°C supply | C-2012 Campus Bay-1 Hall B lease Sched 2, cl 4.2 | 2022-01-01 | Standard |
| Connectivity | Regional Cloud J | Diverse fibre entry into the building | 2 diverse fibre entry points | C-2012 Campus Bay-1 Hall B lease Sched 3, cl 2.4 | 2022-01-01 | Standard |
| Space | Regional Cloud J | Dedicated space allocation | Dedicated hall, caged, 20 MW | C-2012 Campus Bay-1 Hall B lease Sched 1, cl 1.2 | 2022-01-01 | Standard |
| SLA and service credits | Regional Cloud J | Availability target and credit regime | 99.999% uptime, 5% credit per 0.01% | C-2012 Campus Bay-1 Hall B lease Sched 5, cl 2.1 | 2022-01-01 | Standard |
| Expansion rights and ROFR | Regional Cloud J | Right of first refusal on further capacity | ROFR on adjacent hall, 30 day response | C-2012 Campus Bay-1 Hall B lease cl 14.3 | 2022-01-01 | Standard |
| Pricing and indexation | Regional Cloud J | Annual price adjustment | CPI indexation, capped at 3% a year | C-2012 Campus Bay-1 Hall B lease cl 8.5 | 2022-01-01 | Standard |
| Sustainability and renewable energy commitments | Regional Cloud J | Renewable energy matching | 100% renewable energy matched annually | C-2012 Campus Bay-1 Hall B lease Sched 7, cl 1.1 | 2022-01-01 | Standard |
| Security and access | Regional Cloud J | Physical access control | Biometric access, escorted visitors | C-2012 Campus Bay-1 Hall B lease Sched 6, cl 3.2 | 2022-01-01 | Standard |
| Termination and step-in | Regional Cloud J | Termination rights and cure period | Termination for convenience after year 3 | C-2012 Campus Bay-1 Hall B lease cl 21.1 | 2022-01-01 | Non-standard |
| Power | AI Lab K | Maximum IT load density per rack | Max 130 kW per rack | C-2006 Campus North-1 Hall C liquid cooling fit-out Sched 2, cl 3.1 | 2025-02-01 | Non-standard |
| Cooling | AI Lab K | Cooling method and supply temperature | Direct liquid cooling, 30°C supply | C-2006 Campus North-1 Hall C liquid cooling fit-out Sched 2, cl 4.2 | 2025-02-01 | Non-standard |
| Connectivity | AI Lab K | Diverse fibre entry into the building | 2 diverse fibre entry points | C-2006 Campus North-1 Hall C liquid cooling fit-out Sched 3, cl 2.4 | 2025-02-01 | Standard |
| Space | AI Lab K | Dedicated space allocation | Dedicated hall, caged, 30 MW | C-2006 Campus North-1 Hall C liquid cooling fit-out Sched 1, cl 1.2 | 2025-02-01 | Standard |
| SLA and service credits | AI Lab K | Availability target and credit regime | 99.999% uptime, 5% credit per 0.01% | C-2006 Campus North-1 Hall C liquid cooling fit-out Sched 5, cl 2.1 | 2025-02-01 | Standard |
| Expansion rights and ROFR | AI Lab K | Right of first refusal on further capacity | ROFR on full campus, 60 day response | C-2006 Campus North-1 Hall C liquid cooling fit-out cl 14.3 | 2025-02-01 | Non-standard |
| Pricing and indexation | AI Lab K | Annual price adjustment | CPI indexation, capped at 3% a year | C-2006 Campus North-1 Hall C liquid cooling fit-out cl 8.5 | 2025-02-01 | Standard |
| Sustainability and renewable energy commitments | AI Lab K | Renewable energy matching | 100% renewable energy matched annually | C-2006 Campus North-1 Hall C liquid cooling fit-out Sched 7, cl 1.1 | 2025-02-01 | Standard |
| Security and access | AI Lab K | Physical access control | Biometric access, escorted visitors | C-2006 Campus North-1 Hall C liquid cooling fit-out Sched 6, cl 3.2 | 2025-02-01 | Standard |
| Termination and step-in | AI Lab K | Termination rights and cure period | Termination for cause, 90 day cure | C-2006 Campus North-1 Hall C liquid cooling fit-out cl 21.1 | 2025-02-01 | Standard |
| Power | AI Lab L | Maximum IT load density per rack | Max 130 kW per rack | C-2016 Campus Strait-1 Hall B inference pod sale order Sched 2, cl 3.1 | 2026-12-01 | Non-standard |
| Cooling | AI Lab L | Cooling method and supply temperature | Direct liquid cooling, 30°C supply | C-2016 Campus Strait-1 Hall B inference pod sale order Sched 2, cl 4.2 | 2026-12-01 | Non-standard |
| Connectivity | AI Lab L | Diverse fibre entry into the building | 2 diverse fibre entry points | C-2016 Campus Strait-1 Hall B inference pod sale order Sched 3, cl 2.4 | 2026-12-01 | Standard |
| Space | AI Lab L | Dedicated space allocation | Dedicated hall, caged, 40 MW | C-2016 Campus Strait-1 Hall B inference pod sale order Sched 1, cl 1.2 | 2026-12-01 | Standard |
| SLA and service credits | AI Lab L | Availability target and credit regime | 99.999% uptime, 5% credit per 0.01% | C-2016 Campus Strait-1 Hall B inference pod sale order Sched 5, cl 2.1 | 2026-12-01 | Standard |
| Expansion rights and ROFR | AI Lab L | Right of first refusal on further capacity | ROFR on adjacent hall, 30 day response | C-2016 Campus Strait-1 Hall B inference pod sale order cl 14.3 | 2026-12-01 | Standard |
| Pricing and indexation | AI Lab L | Annual price adjustment | CPI indexation, capped at 3% a year | C-2016 Campus Strait-1 Hall B inference pod sale order cl 8.5 | 2026-12-01 | Standard |
| Sustainability and renewable energy commitments | AI Lab L | Renewable energy matching | 100% renewable energy matched annually | C-2016 Campus Strait-1 Hall B inference pod sale order Sched 7, cl 1.1 | 2026-12-01 | Standard |
| Security and access | AI Lab L | Physical access control | Biometric access, escorted visitors | C-2016 Campus Strait-1 Hall B inference pod sale order Sched 6, cl 3.2 | 2026-12-01 | Standard |
| Termination and step-in | AI Lab L | Termination rights and cure period | Termination for cause, 90 day cure | C-2016 Campus Strait-1 Hall B inference pod sale order cl 21.1 | 2026-12-01 | Standard |
| Power | GPU Cloud M | Maximum IT load density per rack | Max 140 kW per rack | C-2007 Campus Strait-1 Hall A GPU lease Sched 2, cl 3.1 | 2024-07-01 | Non-standard |
| Cooling | GPU Cloud M | Cooling method and supply temperature | Direct liquid cooling, 32°C supply | C-2007 Campus Strait-1 Hall A GPU lease Sched 2, cl 4.2 | 2024-07-01 | Non-standard |
| Connectivity | GPU Cloud M | Diverse fibre entry into the building | 2 diverse fibre entry points | C-2007 Campus Strait-1 Hall A GPU lease Sched 3, cl 2.4 | 2024-07-01 | Standard |
| Space | GPU Cloud M | Dedicated space allocation | Dedicated hall, caged, 70 MW | C-2007 Campus Strait-1 Hall A GPU lease Sched 1, cl 1.2 | 2024-07-01 | Standard |
| SLA and service credits | GPU Cloud M | Availability target and credit regime | 99.999% uptime, 5% credit per 0.01% | C-2007 Campus Strait-1 Hall A GPU lease Sched 5, cl 2.1 | 2024-07-01 | Standard |
| Expansion rights and ROFR | GPU Cloud M | Right of first refusal on further capacity | ROFR on adjacent hall, 30 day response | C-2007 Campus Strait-1 Hall A GPU lease cl 14.3 | 2024-07-01 | Standard |
| Pricing and indexation | GPU Cloud M | Annual price adjustment | CPI indexation, capped at 3% a year | C-2007 Campus Strait-1 Hall A GPU lease cl 8.5 | 2024-07-01 | Standard |
| Sustainability and renewable energy commitments | GPU Cloud M | Renewable energy matching | 100% renewable energy matched annually | C-2007 Campus Strait-1 Hall A GPU lease Sched 7, cl 1.1 | 2024-07-01 | Standard |
| Security and access | GPU Cloud M | Physical access control | Biometric access, escorted visitors | C-2007 Campus Strait-1 Hall A GPU lease Sched 6, cl 3.2 | 2024-07-01 | Standard |
| Termination and step-in | GPU Cloud M | Termination rights and cure period | Customer step-in right for cooling plant | C-2007 Campus Strait-1 Hall A GPU lease cl 21.1 | 2024-07-01 | Non-standard |