Active Risks
2
Active Issues
2
High / critical
4
Overdue actions
0
6 of 6 records
| ID / Type | Risk or issue | Account / Contract | Delivery references | Priority | Status | Owner / Due | |
|---|---|---|---|---|---|---|---|
RI-1001 Risk | Campus East-1 renewal commercial terms unresolved Agree pricing guardrails with procurement before the renewal review. | Hyperscaler A | PRJ-TYO-27 Sprint: SPR-24 Epic: EPIC-RENEW-01 Work item: TASK-431 | High | Open | Priya Nair 2026-11-06 | |
RI-1002 Issue | Campus Strait-1 coolant temperature above target Inspect CDU controls and validate temperatures under load. | GPU Cloud M | PRJ-JHB-GPU Sprint: SPR-24 Epic: EPIC-COOL-02 Work item: BUG-882 | Critical | In progress | Aiko Tanaka 2026-10-26 | |
RI-1003 Risk | Liquid cooling fit-out delivery slippage Secure alternate supplier and confirm delivery milestones. | AI Lab K | PRJ-SYD-LC Sprint: SPR-25 Epic: EPIC-FITOUT-03 Work item: TASK-512 | High | Open | Priya Nair 2026-11-12 | |
RI-1004 Issue | Campus Harbour-1 cooling unit fault Replace module and confirm stable cooling with site operations. | Platform G | PRJ-SGP-OPS Sprint: SPR-24 Epic: EPIC-RELIAB-04 Work item: BUG-881 | High | In progress | Wei Chen 2026-10-25 | |
RI-1005 Risk | Campus South-1 renewal approval dependency Approval dates agreed; monitor milestones weekly. | Hyperscaler C | PRJ-MEL-RENEW Sprint: SPR-25 Epic: EPIC-RENEW-01 Work item: TASK-433 | Medium | Mitigated | Priya Nair 2026-11-20 | |
RI-1006 Issue | Campus North-1 feeder breaker investigation complete Corrective maintenance completed and customer report issued. | Hyperscaler B | PRJ-SYD-OPS Sprint: SPR-23 Epic: EPIC-POWER-05 Work item: BUG-888 | Medium | Closed | Tom Hughes 2026-10-20 |