Platform E APAC MSA
C-2014 · Master Agreement · Platform E
Campus
Campus Harbour-1
MW
-
Term
2023-01-01 to 2033-01-01
Status
Active
| Category | Account | Term | Value | Source and clause | Effective | Position |
|---|---|---|---|---|---|---|
| Power | Platform E | Maximum IT load density per rack | Max 50 kW per rack, N+1 supply | C-2014 Platform E APAC MSA Sched 2, cl 3.1 | 2023-01-01 | Standard |
| Cooling | Platform E | Cooling method and supply temperature | Air cooled, 27°C supply | C-2014 Platform E APAC MSA Sched 2, cl 4.2 | 2023-01-01 | Standard |
| Connectivity | Platform E | Diverse fibre entry into the building | 2 diverse fibre entry points | C-2014 Platform E APAC MSA Sched 3, cl 2.4 | 2023-01-01 | Standard |
| Space | Platform E | Dedicated space allocation | Dedicated hall, caged, 95 MW | C-2014 Platform E APAC MSA Sched 1, cl 1.2 | 2023-01-01 | Standard |
| SLA and service credits | Platform E | Availability target and credit regime | 99.999% uptime, 5% credit per 0.01% | C-2014 Platform E APAC MSA Sched 5, cl 2.1 | 2023-01-01 | Standard |
| Expansion rights and ROFR | Platform E | Right of first refusal on further capacity | ROFR on adjacent hall, 30 day response | C-2014 Platform E APAC MSA cl 14.3 | 2023-01-01 | Standard |
| Pricing and indexation | Platform E | Annual price adjustment | CPI indexation, capped at 3% a year | C-2014 Platform E APAC MSA cl 8.5 | 2023-01-01 | Standard |
| Sustainability and renewable energy commitments | Platform E | Renewable energy matching | 24/7 carbon-free energy by 2030 | C-2014 Platform E APAC MSA Sched 7, cl 1.1 | 2023-01-01 | Non-standard |
| Security and access | Platform E | Physical access control | Biometric access, escorted visitors | C-2014 Platform E APAC MSA Sched 6, cl 3.2 | 2023-01-01 | Standard |
| Termination and step-in | Platform E | Termination rights and cure period | Termination for cause, 90 day cure | C-2014 Platform E APAC MSA cl 21.1 | 2023-01-01 | Standard |