Risks & Issues register
1 records · APAC portfolio
Active Risks
0
Active Issues
0
High / critical
0
Overdue actions
0
1 of 6 records
| ID / Type | Risk or issue | Account / Contract | Delivery references | Priority | Status | Owner / Due | |
|---|---|---|---|---|---|---|---|
RI-1006 Issue | Campus North-1 feeder breaker investigation complete Corrective maintenance completed and customer report issued. | Hyperscaler B | PRJ-SYD-OPS Sprint: SPR-23 Epic: EPIC-POWER-05 Work item: BUG-888 | Medium | Closed | Tom Hughes 2026-10-20 |